SIGMA LITHIUM AWARDED THE ENVIRONMENTAL OPERATING LICENSE WITH UNANIMOUS APPROVAL AND SCALES UP SOCIAL INITIATIVES; FIRST PRODUCTION ON SCHEDULE TO COMMENCE IN APRIL 2023

Retrieved on: 
Monday, April 10, 2023

On March 31, 2023, Sigma Lithium was awarded its environmental operating license (LO), permitting the company to produce Green Lithium, with unanimous vote of approval including from all the NGOs with a seat at the CMI.

Key Points: 
  • On March 31, 2023, Sigma Lithium was awarded its environmental operating license (LO), permitting the company to produce Green Lithium, with unanimous vote of approval including from all the NGOs with a seat at the CMI.
  • The LO enables the company to sell all Green Lithium product from current and future production, including any stockpiled product.
  • This follows the successful completion of crushing circuit commissioning of the Greentech Plant as announced on February 13, 2023.
  • Sigma Lithium has held the required dual environmental licenses for both construction and initiation of its wholly owned Grota do Cirilo project since 2019.

Sigma Lithium Starts Construction Of Production Plant Foundation And Infrastructure And Orders Long Lead Items, On Schedule For Production In 2022

Retrieved on: 
Monday, December 6, 2021

Sigma starts construction activities on site for foundation, earth civil works and infrastructure installation of Production Plant, with equipment and 180 workers.

Key Points: 
  • Sigma starts construction activities on site for foundation, earth civil works and infrastructure installation of Production Plant, with equipment and 180 workers.
  • Sigma ordered an increased number of 38 key long lead items, placing deposits to secure them and maintain the current timeline for Production Plant commissioning.
  • Completion of this stage of the construction civil works is expected within three months, when the Brazilian sub-construction firm of Promon Engenharia Ltda.
  • In order to fund construction, the Company has the funds to meet the equity funding requirements under its proposed construction bank debt facility.