G Mining Ventures Provides Update on Site Activities at Tocantinzinho Gold Project
Retrieved on:
星期二, 六月 13, 2023
Mining, Workforce, Feasibility study, Hazard and operability study, Ouro, CIL, Novo Progresso, Process automation system, TZ, Engineering, Technical report, 3D, Sewage, Water, Brazilians, Corporation, QA/QC, Fruit, Oil, Supervisory control, Photography, Long Harbour Nickel Processing Plant, QP, SAG, Novo, Project, Total project control, ESG, Health, KV, CAT, FTSF, Completion, Safety, Construction, Heavy equipment, Instrumentation, Landfill, Dam, Uranium mining, SCADA, QC, Sedar
BROSSARD, QC, June 13, 2023 /PRNewswire/ - G Mining Ventures Corp. ("GMIN" or the "Corporation") (TSXV: GMIN) (OTCQX: GMINF) is pleased to provide an update on progress made at GMIN's 100% owned Tocantinzinho Gold Project ("TZ" or the "Project") currently under construction in the State of Pará, Brazil.
Key Points:
- BROSSARD, QC, June 13, 2023 /PRNewswire/ - G Mining Ventures Corp. ("GMIN" or the "Corporation") (TSXV: GMIN) (OTCQX: GMINF) is pleased to provide an update on progress made at GMIN's 100% owned Tocantinzinho Gold Project ("TZ" or the "Project") currently under construction in the State of Pará, Brazil.
- Total Project is currently 30% complete and trending on time and on budget for commercial production in H2-24.
- Commitments to date total $302 million (66% of project total), including project-to-date expenditures of $198 million (43% of project total).
- Cumulatively, 33,334 tonnes of material on 3,833 truckloads have been delivered to site since the start of the Project.