Mitsubishi Power Begins Commercial Operation of Fifth M701JAC Gas Turbine in Thailand GTCC Power Plant Project
Retrieved on:
Wednesday, April 19, 2023
Mitsubishi Power has delivered five of the gas turbines within the contract delivery period, and the two plants are expected to be in commercial operation by October 2024.
Key Points:
- Mitsubishi Power has delivered five of the gas turbines within the contract delivery period, and the two plants are expected to be in commercial operation by October 2024.
- All four units of the Chonburi power plant commenced commercial operation in October 2022 and have exceeded 25,000 actual operating hours (AOH), demonstrating the reliability of the state-of-the-art JAC gas turbines.
- The overall project encompasses two GTCC power generation plants, each with four power trains comprising a gas turbine, steam turbine, heat recovery steam generator, and generator.
- We look forward to continued collaboration with Mitsubishi Power and other partners to ensure the success of this project."