Iris Energy Limited Announces Monthly Investor Update for February 2022
Retrieved on:
Tuesday, March 8, 2022
Bitcoin, Playoffs, Fernie Ghostriders, KIJHL, Childress County, Texas, Research, AEP, Growth, BC Hydro, Miner, Company, Conference, Canal Flats, Work, American Electric Power, Engineering, Kootenay International Junior Hockey League, Foundation, Airline, Bookkeeping, Life insurance, Oil, Cryptocurrency, Construction, Renewable energy, Machine shop, Silviculture, Rocky Mountains
SYDNEY, Australia, March 08, 2022 (GLOBE NEWSWIRE) -- Iris Energy Limited (NASDAQ: IREN) (“Iris Energy” or “the Company”), a leading sustainable Bitcoin miner which is building an institutional grade infrastructure platform with 15 EH/s of secured miners (10 EH/s expected to be operational by early 2023), today published a monthly investor update for February 2022, containing its results from operations as well as construction and development updates.
Key Points:
- Canal Flats update (0.8 EH/s, 30MW) BC, Canada
The project achieved monthly average operating hashrate of 844 PH/s in February 2022 (vs. 804 PH/s in January 2022). - The 5% increase in hashrate was driven by the installation of new latest generation hardware to replace existing lower efficiency hardware.
- The first 0.3 EH/s (9MW) remains ahead of schedule with the anticipated operational start date in early Q2 2022.
- In addition to targeting markets with abundant and/or under-utilized renewable energy, Iris Energy seeks to partner with the local communities in which we operate.