LTSA

Second Unit of M701JAC Gas Turbine Begins Commercial Operation at GTCC Power Plant in Chonburi Province, Thailand

Monday, October 11, 2021 - 3:44am

The first unit, which was also a first M701JAC in Southeast Asia, started commercial operation at the end of March this year.

Key Points: 
  • The first unit, which was also a first M701JAC in Southeast Asia, started commercial operation at the end of March this year.
  • When completed, the eight units in the project will form a gas turbine combined cycle (GTCC) power system with a total output of 5,300 megawatts (MW).
  • Koji Nishikawa, President and Managing Director of Mitsubishi Power (Thailand), spoke of his company's commitment to its work in Thailand.
  • The newly inaugurated M701JAC is a core component of the power plant in Chonburi Province, which is operated by Gulf SRC Company Limited*.