Perforation operations will then begin with the lowest zone of interest (L2.6) and then running a testing tubing string with straddle packers to test the isolated L2.6 zone.
Key Points:
- Perforation operations will then begin with the lowest zone of interest (L2.6) and then running a testing tubing string with straddle packers to test the isolated L2.6 zone.
- This will be followed by pulling the 5 inch casing that is inside the 9 inch casing and running cased hole reservoir logs.
- Additional early production and central processing facilities will be added as required to accommodate additional production levels from field development activities.
- We look forward to ramping up production as we continue to progress full-field development at the Oza Field.