Province of Genoa

Genova San Giorgio bridge: RINA at the helm of a great Italian engineering success

Retrieved on: 
Monday, August 3, 2020

The "Genoa model" is the result of total commitment and round-the-clock management and supervision

Key Points: 
  • The "Genoa model" is the result of total commitment and round-the-clock management and supervision
    GENOA, Italy, Aug. 3, 2020 /PRNewswire/ -- The Genova San Giorgio bridge reopened just 15 months from the start of construction work.
  • The numbers make interesting reading, there were over 220,000 hours of engineering work generating more than 3,200 technical documents and reviewing over 1,500 project sheets.
  • A team of 80 RINA specialists was dedicated to managing the project guiding the construction phases, timelines, budgets and progress of the work.
  • There were 20 sites operating simultaneously, 7 days a week, 24 hours a day without interruption for almost two years, apart from Christmas Day in 2019.