B2Gold Announces Goose Project Update; Project Construction and Development on Track for First Gold Production in Q2 2025; Total Construction and Mine Development Cash Expenditure Estimate Before First Gold Production Revised to Reflect Current Timeline
All vessels are expected to have completed the offload of supplies to the MLA by October 2024.
- All vessels are expected to have completed the offload of supplies to the MLA by October 2024.
- The acceleration of certain capital items is expected to make the Goose Project a more reliable and de-risked operation upon mill startup.
- The Company continues to estimate that gold production in calendar year 2025 will be between 120,000 ounces and 150,000 ounces.
- B2Gold successfully completed the 2024 WIR campaign and has delivered all necessary materials from the MLA to complete the construction of the Goose Project.